Standard Project Assumptions
Last Modified: May 1, 2023
| Governance & Controls | Customer |
|---|---|
| Project Management (Company) | |
| 1 Define & establish the governance model. | C |
| 2 Day-to-day management, planning, and allocation of Company resources are required to implement the project. | I |
| 3 Progress reporting on Company work. | I |
| 4 Project Team Meetings; scheduling, reporting, documentation of minutes & actions. | C |
| 5 Management of project Risks, Actions, Issues & Decisions (RAID) log. | C |
| 6 Completion of Company deliverables as set forth in this SOW. | I |
| Project Management (Customer) | |
| 7 Day-to-day management, planning, resource allocation of Customer resources required to implement the project. | A/R |
| 8 Progress reporting on Customer deliverables. | A/R |
| 9 Management of assigned project Risks, Actions, Issues & Decisions. | A/R |
| 10 Completion of Customer deliverables as requested by Company in service of this project. | A/R |
| General Governance | |
| 11 Project Steering Committee / Board; scheduling of meetings, reporting, documentation of minutes & actions. | C |
| 12 Company Implementation Schedule & Phased Project Plan development. | C |
| 13 Budget management and reporting for Company implementation services. | I |
| 14 Preparation of Change Control documentation, including impact assessment. | C |
| 15 Review and approval of Change Control (change orders, contract variations). | A/R |
| 16 Review and approval of Project Plan Baselines (via Project Board). | A/R |
| Phase 1: Initiation | Customer |
|---|---|
| Initiation Activities | |
| 1 Customer stakeholder identification for inclusion in Project Initiation Documentation. | A/R |
| 2 Customer stakeholder communications plan. | A/R |
| 3 Appointment of customer project board and team positions (including Project Manager, Project Sponsor and Business Owner). | A/R |
| 4 Creation and provision of the detailed project implementation plan (to be baselined at Project Board). | C |
| 5 Confirmation of Company resources and team structure, including roles and responsibilities. | I |
| 6 Creation of Summary Project Initiation Document. | C |
| Kick Off Meeting / Workshop | |
| 7 Preparation of all collateral for Kick Off Meeting. | C |
| 8 Confirmation of customer attendees, logistics and invitations. | A/R |
| 9 Creation of Summary Project Initiation Document. | C |
| Phase 2: Design | Customer |
|---|---|
| Workshop Preparation & Execution | |
| 1 Creation & provision of Design Workshop Terms of Reference. | I |
| 2 Provision of any pre-Workshop discovery requests and clarifications made by Company. | A/R |
| 3 Identification, and confirmation of attendance, of key Customer representatives with appropriate design authority and understanding of Customer business rules (i.e. Segmentation etc). | A/R |
| 4 Identification, and confirmation of availability, of Customer 3rd party integrated systems Subject Matter Experts (i.e. POS, Web, Mobile and CRM systems). | A/R |
| 5 Preparation of the Workshop agenda, collateral and other presentation material. | I |
| 6 Organisation & booking of Workshop venue and associated logistics (for in person sessions at Customer offices). | A/R |
| 7 Provision of Company documentation (including API specifications, data load templates). | I |
| 8 Provision of all Customer Copy, and creative assets, for inclusion in the build, as requested by Company Project Manager. | A/R |
| 9 Confirmation of delegates, and attendance at, the Company Adoption Services training sessions as advised by Company Project Manager. | A/R |
| Workshop Outputs | |
| 10 Documentation of Workshop design agreements and follow-up items. | C |
| 11 Review and feedback of any documented workshop outputs as requested by Company Project Manager. | A/R |
| 12 Creation of Solution Specification Document (SSD) as informed by Workshop agreements. | I |
| 13 Solution Specification Document review and signoff as requested by Company Project Manager, and as per baselined schedule. | A/R |
| 14 Provision of sample Data as requested by Company Project Manager. | A/R |
| Environment Provisioning | |
| 15 Provisioning of Company Environment(s) for Engage and Site. | I |
| 16 Provision of sample data and IP’s for SFTP Whitelisting. | A/R |
| 17 Provision of Customer user list and system role definitions as requested by Company Project Manager. | A/R |
| Phase 3: Build | Customer |
|---|---|
| Configuration, Build & Data Migration | |
| 1 Configuration of in-scope Company Products as per Solution Specification Document (including unit testing). | I |
| 2 Configuration of any 3rd party systems required for integration. | A/R |
| 3 Provision of data required for data loading, or population of data load templates, as requested by Company Project Manager. | A/R |
| 4 Assurance of quality and completeness, including remediation, of any data provided to Company for data import. | A/R |
| 5 Resolution of mutually agreed configuration defects raised during formal User Test cycles. | C |
| Production Deployment & Core Team Enablement | |
| 6 Configuration & verification of Company’s Environment(s) as per Solution Specification Document. | C |
| 7 Provision of final solution walkthrough to Customer Core Project Team. | C |
| Phase 4: Implementation | Customer | Company |
|---|---|---|
| BAU Enablement | ||
| 1 Initiation and provision of Post Go-Live Support (level of cover is set forth in Scope & Assumptions) | I | A/R |
| 2 Allocation of BAU System Owner(s) and competent resources for ongoing operational use of the delivered solution. | A/R | C |
| 3 Provision of Technical Enablement and End User Enablement training (as set forth in the applicable SOW). | C | A/R |
| 4 Provision of Coaching support (as set forth in the applicable SOW) | C | A/R |
| 5 Completion of the Handover to Support process, including Customer briefing session. | C | A/R |
| 6 Provisioning of full and final Customer Users, as per license agreement, in Company’s Environment. | I | A/R |
| 7 Creation and execution of Customer internal communications plan | A/R | C |
| 8 Creation of IP Warming plan. | C | A/R |
| 9 Provision of engagement data required for IP Warming. | A/R | C |
| Go-Live | ||
| 9 Creation of the detailed Go-Live plan. | C | A/R |
| 10 Provision of the Go-Live Readiness Report. | C | A/R |
| 11 Go/No-Go Meeting & Final Decision. | A/R | C |
| 12 Execution of final data load activity in support of Go-Live event. | A/R | C |
| Phase 5: Close | Customer | Company |
|---|---|---|
| Preparation for Close | ||
| 1 Completion of Customer handback to Customer Success & Engagement Management. | I | A/R |
| 2 Customer agreement & execution of ongoing Services Retainer (based on Customer need for ongoing support). | A/R | C |
| 3 Confirmation of Project Completion | R | A |
| 4 [If applicable] [Optional] Approval & confirmation of Customer References. | R | A |
| 5 [If applicable] [Optional] Review & approval of Customer Case Study. | R | A |
| Formal Close | ||
| 6 Provision of Project Completion Report, including closing position on financials and delivered scope. | C | A/R |
| 7 Final review of Risks, Issues and Lessons Learned logs. | C | A/R |
| 8 Final Project Board Meeting (including approval to close the project, final actions review & any agreed follow up activity). | C | A/R |